View Full Version : Planning Module For OPM
zobibhai
07-29-2008, 04:22 AM
Dear All
Can you please guide me as to which planning module we can implement using R12 OPM. Do we have to use ASCP or we can use OPM MRP. Our requirements are not very complex.
Note : we are implementing R12 OPM in a steel plant.
Thanks in advance,
Zohaib Khan
uttamde
07-30-2008, 01:11 AM
Hi,
You have to use ASCP with OPM in R12 OPM.You can use either Unconstrained or Constrained based ASCP as per your requirement.
OPM MRP was 11i OPM feature.
Regards
zobibhai
07-30-2008, 05:27 AM
Hi,
Thank you vey much. Can you please also guide me as to what are the minumum modules in OPM we should consider to implement.
Thanks in advance,
Zohaib
uttamde
07-30-2008, 07:43 AM
Hi,
For OPM R12, you have to use following applications:-
Process Manufacturing Product Development,
Process Manufacturing Process Execution,
Process Manufacturing Process Planning,
Process Manufacturing Financials,
Advanced Supply Chain Planning
And all other applications like payble,inventory etc. are similar to discrete manufacturing.
So, you have to choose as per your requirement.
Regards
rameshbvm
10-20-2008, 05:29 AM
Hi Friends
Can anyone guide me in implementing OPM Planning in R12 OPM? The responsibilty OPM Process planning doesnt seem to work in R12.What is the alternate responsibilty which I should use? Awaiting for your valuable suggestions and comments..
Thanks
Ramesh